Construction Updates by Building
(links marked with * are .pdf and require Adobe Reader)

Building 1 | Building 2 | Building 3 | Building 4 | Building 5 | Building 6 | Building 7 | Building 8 | Building 9 | Building 10 | Building 11 | Building 12 | Building 13 | Building 15 | Building 16 | Building 17 | Building 18 | Building 19 | Building 24-27 | Center | Airport | Downtown Campus Building | Florence Center | Parking Lots | Solar Station | Track and Soccer Bowl

Building 3

February 2, 2010
ALL DEFERRED MAINTENANCE PROJECTS COMPLETE

August 31, 2009
PROJECT 451 UTILITY SUBMETERING

Completed meter installations this week: water meters for buildings 1, 2, and 5; electrical meters for buildings 1, 2, 3, 4, 5, 6, 7, 11, 18, 19, 24, 25, 26, and 27. Main building isolation valve replacements this week: domestic cold water in buildings 4, 5, and 6. In addition, eight water main valves were replaced. Contact Angela Fazio, 463-3428.

August 18, 2009
PROJECT 451 UTILITY SUBMETERING

The following meter installations were completed this week: water, buildings 4, 17, 18, and 19; natural gas, building 19. Main isolation valve replacements this week: domestic cold water, buildings 2, 3, 18, and 19. Contact Angela Fazio, 463-3428.

August 10, 2009
UTILITY SHUT DOWN SCHEDULED FOR AUGUST 21, 22, AND 23, 2009
Electricity will be shut down in Building 3 on August 22 and 23. Contact Mark Richardson, 463-3426.

PROJECT 451 UTILITY SUBMETERING
EMK is currently working on installing irrigation meters throughout the campus. On August 7, water and gas services will be shut off. for Buildings 3, 9, 15, and 16. Power will be shut down on August 7 from 7:00 a.m. – 7:00 p.m. in Buildings 1, 2 and Center. Contact Mark Richardson, 463-3426.

July 21, 2009
PROJECT 447 CARPET REPLACEMENT/FLOOR COVERING

Carpet and linoleum installation in four classrooms in building 12 is expected to be completed the week of July 20. Next, carpet will be installed in classrooms on the Center fourth floor. Carpet replacement is also scheduled for building 6 rooms 140 and 126 the week of July 27. Beginning the second week of August, another large shipment of carpet will be delivered for buildings 19, 3, and 15 and Florence. Contact Mark Richardson, 463-3426.


>> Return to Lane's Homepage     >> Return to Facilities Management and Planning Main Page     >> Return to top of page

Lane Community College - Facilities Management and Planning - Building 7, Room 204